Nigeria to increase power supply by 817MWs – TCN

0
222
Read audio

According to the Federal Government, efforts are being made to increase the amount of electricity available in the FCT and its surroundings by adding an additional 817 Megawatts (MWs) to the national grid.

This was said on Wednesday in Abuja by Mr Sule Abdulaziz, the Managing Director of Transmission Company of Nigeria (TCN), who was visiting ongoing projects in the Federal Capital Territory (FCT).

Abdulaziz said that the French Development Agency (AFD), a donor organization, was providing funding for the project, which belonged to TCN and was known as the Abuja Feeding Scheme.

When finished, he claimed, it would add 1. 465 more transmission lines to the grid, improving and strengthening the FCT’s access to electricity.

“With the additional lines, TCN capacity of transmission lines will be higher than what is in existence and this means that in future, we can build some sub-stations without upgrading the lines,” he said.
According to him, the project will add five transmission substations, 143 kilometers of 330 Kilo Volts (KVs) and 81 kilometers of 132 KV transmission lines to Abuja.

“This is part of efforts to increase transmission wheeling capacity in the FCT and environs.

“The project is categorised into six lots and is far advanced in execution above 85 per cent in total completion by December, ‘’ he said.

The managing director said that the project was designed by the current administration to ensure that in the next 50 years, there would be no need for other substations in the FCT.

“ This will be adequate and it will serve the population of Abuja, ’he said.

“The government while making plans for the project has in mind that if the population of FCT increases within five to 10 years, there is a master plan that the station will serve the territory in the next 50 years.

“ Construction of complete new 2x60MVA, 132/33 KV substation with 132KV line Bays at Wumba/Lokogoma including about 5km 132 underground XLPE Cable from New Apo Sub Station are ongoing, ‘’he said.

Others include the 2x150MVA 330/132/33KV substation being built at New Apo, where the managing director grouses about the contractor’s sluggish progress.

He claims that General Electric, the contractor, has performed appallingly.

He questioned why the speed of work was so slow, claiming that all of the substation contracts were signed at the same time.

“We have spent a lot of money to clear their containers which entered demurrage and this money is not part of AFD grant but TCN Internally Generated Revenue which could have been used for other projects.

“We are going to push them to finish the project on time, ‘’ he said.

Sites visited include the construction of complete new 2x60Mega Volt Ampere and 132/33KV Gas Insulated Switchgear (GIS) Substation at Gwarimpa.

Others were the Kuje 132Kv Transmission line, the 3x60MVA, 132/33kv and 4x132kv Line bay GIS, and 33KV Metal Chad Switchgear at West Main Lugbe, Substation.