General Electric pulls out of $2 billion Nigeria rail concession deal

0
921
Workers stand along a prototype rail line, to be constructed by China Railway Construction Corporation (CRCC), during the ground breaking for the construction of Lagos-Ibadan rail line project at the Ebute-Metta headquarters of the Nigerian Railway Corporation in Lagos on March 7, 2017. Nigeria's acting President Yemi Osinbajo has signed off on the construction of the Lagos-Ibadan double track railway line modernisation project to be executed by the China Railway Construction Corporation (CRCC). The project, when completed, will open up direct transit from the coastal city of Lagos, Nigeria's commercial capital, to Ibadan, in the heart of the south west. / AFP PHOTO / PIUS UTOMI EKPEI

Alexis Akwagyiram

LAGOS, Nov 14 – General Electric Co has pulled out of a long-term concession deal with the Nigerian government to maintain and operate narrow-gauge rail lines in the West African country, a procurement process adviser told Naija247news on Wednesday.

The Nigerian railway concession project was worth around $2 billion for two lines connecting northern cities to others in the south.

The government had been due to enter into negotiations last year with GE over a railway project, although Nigeria’s upper house of parliament had said it would probe the railway concession over possible violations by Nigerian officials.

It was not clear why GE pulled out of the concession. The company was not immediately available for comment.

A consortium led by GE had submitted the only bid for the project in partnership with Transnet of South Africa, Dutch-based APM Terminals and China’s Sinohydro Consortium.

Fola Fagbule, senior vice president and head of advisory at Africa Finance Corporation (AFC), which ran the procurement process after being appointed lead adviser by the government, said Transnet was in discussion to replace GE.

Economic growth in Africa’s most populous nation has been hampered for decades by its dilapidated rail network, built mainly by British colonial rulers before independence in 1960.

The concession was meant to cover about 3,500 km (2,200 miles) of existing narrow-gauge lines from the southwestern commercial capital, Lagos, to Kano in the north and from southeastern oil hub Port Harcourt to Maiduguri in the northeast.